Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Calculation of Damages & Liquidated Damages: The Egyptian Perspective

Author: Ibrahim Shehata

This article discusses the issue of contractual damages under Egyptian Law in light of the recent court trends in the past decade. First of all, the general rule dictates that the basic elements of liability must be present (fault, damage, and causal link) in order that the claimant is awarded damages. In this regard, this article focuses on four issues, namely, (a) calculation of damages; and (b) liquidated damages.

Calculation of Damages:

In 2018, the Court of Cassation has conducted a detailed study of the aspects relating to the calculation of damages. First, the Court underlined that pursuant to articles (170), (221) and (222) of the Civil Code, compensation is based on the principle of full compensation, as the Court must remediate every direct damage whether it was physical or moral including the direct loss and the loss of expected profits. This is because the goal of the principle of full compensation is to restore the creditor to its prior position before the mistake took place. However, the Court of Cassation emphasized that the scope of compensation in the case of tortious liability is broader than that in the realm of contractual liability. In the case of tortious liability, the compensation of both foreseeable harm and unforeseeable harm are included when calculating the damages. As for contractual liability, the compensation is limited to the foreseeable harm in the moment of the conclusion of the contract as long as there is no fraud or gross negligence by one of the parties. The Court of Cassation highlighted that the loss of expected gains or profits has a special nature that requires a special treatment that results in the application of a less stringent standard of proof, as the concerned party is only required to prove a but-for-scenario that did not take place in reality.

In this regard, the Court of Cassation has held that the most significant factors that the court could draw in assessing the adequacy of evidence of loss of profits are the following

  • The degree to which it is assumed that damage has already been done to the creditor;
  • Whether the creditor has provided the best possible evidence to establish the loss of profits;
  • The nature of the debtor’s mistake, tortious or contractual, intentionally or not;
  • The extent to which the creditor knows about the market conditions and risks;
  • Whether the creditor’s activity has a previous record of profits or is based upon the promotion of a new service or product that has not been brought before;
  • The reasonableness of the amount claimed in relation to the nature of the economic activity in question; and
  • The degree of the Court’s assurance to the method of calculating the loss of profits, whether by the creditor or the expert appointed by the Court.

Liquidated Damages:

In application of article (223) of the Civil Code, the Court of Cassation considers that the parties to a contract could agree in advance upon the value of compensation by stating such value in a clause within the same contract or under a subsequent agreement. Nevertheless, if the contract is terminated by the creditor due to non-performance instead of claiming liquidated damages, the whole contract and the agreed-upon liquidated damages become terminated and the creditor could only then have recourse to the court to claim compensation in accordance with the general rules for the calculation of damages as mentioned above. It must be noted that in case the creditor is contributing to the delays of the debtor, the creditor may not be awarded any liquidated damages for such delays.

It was also established that for liquidated damages to be awarded, the basic elements of liability must be present (fault, damage, and causal link). The only difference is that the parties by virtue of the liquidated damages clause have foreseen the damages, and hence, the creditor will not have the obligation to prove the extent of damages. In the case where liquidated damages were found to be exaggerated, or if the debtor has executed part of its contractual obligations, it is within the court’s discretionary powers to reduce the value of such compensation.